By Dong-hyeon Park on 28 December 2013

Here is a general work plan for Sphynx project, with the final goal being a paper ready by end of April.
I think we could have two groups working in parallel; One group working on setting up the simulator and running the test, while the other writes scripts to extract the result and analyze it.

Deadline Duration Task #1 Task #2
Jan. 27 ~3 weeks Pick Simulator & Machine Pick Benchmarks and Test Programs
Feb. 17 3 weeks Try Different Hardware Config Write Scripts to Extract Simulation Results
Mar. 17 4 weeks Simulate Simple Cache Config Process and Analyze Result
Apr. 7 3 weeks Simulate Complex Cache Config Start Writing Paper
May. 5 X More Targeted Simulations Finalize Paper