Sphynx Project Work Plan
By Dong-hyeon Park on
28 December 2013
Here is a general work plan for Sphynx project, with the final goal being a paper ready by end of April.
I think we could have two groups working in parallel; One group working on setting up the simulator and running the test, while the other writes scripts to extract the result and analyze it.
Deadline | Duration | Task #1 | Task #2 |
---|---|---|---|
Jan. 27 | ~3 weeks | Pick Simulator & Machine | Pick Benchmarks and Test Programs |
Feb. 17 | 3 weeks | Try Different Hardware Config | Write Scripts to Extract Simulation Results |
Mar. 17 | 4 weeks | Simulate Simple Cache Config | Process and Analyze Result |
Apr. 7 | 3 weeks | Simulate Complex Cache Config | Start Writing Paper |
May. 5 | X | More Targeted Simulations | Finalize Paper |